Ontario Supporting Plan to Refurbish Pickering Nuclear Generating Station
Pickering would supply reliable, low-cost and emissions-free power for an additional 30 years
The Ontario government is supporting Ontario Power Generation’s (OPG) plan to proceed with the next steps toward refurbishing Pickering Nuclear Generating Station’s “B” units (units 5-8). Once refurbished, Pickering would produce a total of 2,000 megawatts (MW) of electricity, equivalent to powering two million homes, helping to meet increasing demand from electrification and fuelling the province’s economic growth.
OPG will now proceed with the Project Initiation Phase of refurbishment which will last through the end of 2024. The government is supporting OPG’s $2 billion budget for this phase which includes engineering and design work as well as securing long-lead components that can require years for manufacturing. By placing orders in advance with key suppliers, OPG will ensure materials are available when Ontario needs them and help keep costs down. OPG and its business partners will also identify potential Indigenous engagement opportunities in contracting, employment and other economic benefits related to the project.
The refurbishment of the Pickering Nuclear Generating Station is just one part of Powering Ontario’s Growth, the government’s pragmatic plan which outlines the actions the province is taking to meet electricity demand and reduce emissions by supporting the electrification of the province’s overall economy over the long-term, including:
- Nuclear Energy – Advancing reliable, affordable and clean nuclear power through pre-development work at Bruce Power and three additional small modular reactors at Darlington
- Competitive Procurements – Acquiring 4,000 MW of storage and natural gas generation and launching more competitive procurements for non-emitting electricity resources including wind, solar, hydroelectric, batteries and biogas.
- New Transmission Infrastructure – Designating and prioritizing transmissions lines in Southwestern and Northeastern Ontario that will power job creators including EV and EV battery manufacturing and clean steel production.
- Keeping Costs Down – Reducing demand through the expansion of Ontario’s energy efficiency programs.
- Planning for Future Transmission – Directing IESO to report back to the Minister with transmission options to address system bottlenecks between Toronto and northern Ontario, and into downtown Toronto, to enable growth. Working with Hydro Québec to explore new transmission connections to support the export of additional excess electricity to Québec.
Ontario will follow a multi-phase approvals process to ensure the Pickering refurbishment project only proceeds if it is in the best interests of Ontario and its ratepayers.
The refurbishment of Pickering Nuclear Generating Station’s “B” units is also subject to regulatory approval by the Canadian Nuclear Safety Commission (CNSC), following a rigorous and transparent process. The CNSC is the federal nuclear regulator responsible for licensing nuclear power plants and overseeing their safe operation in Canada.
Read more: Ontario Supporting Plan to Refurbish Pickering Nuclear Generating Station | Ontario Newsroom